An installation and commissioning record for a gas boiler. Scan the data plate and measure the distance from the flue terminal to the nearest opening from a photo. Enter the limits from the manufacturer's instructions, and the form checks the terminal distance, the working inlet pressure and the CO and CO/CO2 ratio at maximum and minimum rate against them, and counts the results that need attention. Record the system clean, inhibitor and filter, the controls, the carbon monoxide alarm, the notification reference, the Benchmark checklist and the handover. Try the form below, see every question or open a completed example.
✎Every question is editable. Add this form to your account, then change the wording, add or remove questions and options, and make it fit your own jobs.
The Gas Safe registered business that installed the boiler notifies building control through the competent person scheme, and the homeowner then receives a Building Regulations compliance certificate. GOV.UK says a scheme installer gives the certificate within 8 weeks of completion. The installer also completes the Benchmark commissioning checklist, which Benchmark says is a means of meeting the commissioning requirements of Part L.
Record the commissioning at the boiler on a phone. Measure the flue terminal's distance to the nearest opening from a photo, and enter the limits from the manufacturer's instructions: the form checks the terminal distance, the inlet pressure and the CO and CO/CO2 ratio at both rates against them and counts anything that needs attention. It is your site record; the Benchmark checklist and the Building Regulations notification are separate.
Combustion against the manufacturer's limits
Enter the highest CO and CO/CO2 ratio the manufacturer's instructions allow, then the analyser readings at maximum and minimum rate. The form marks each rate within the limits or over a limit, with a red note to investigate before handover.
Photograph the wall square on and measure from the terminal to the nearest opening, using the door as the reference. The form compares it with the minimum in the instructions; anywhere close, check with a tape. It works on web forms in any phone browser today, and the app version is on its way.
A fictional combi boiler replacement in Swindon: tightness test passed, 20.5 mbar working inlet pressure against a 17 mbar minimum, CO and the CO/CO2 ratio within the manufacturer's limits at both rates, the flue terminal about 1.14 m from the back door and its fanlight, CO alarm fitted and the notification reference recorded. Open it as a filled-in form, or switch to a blank copy and try it yourself.
Flue terminal to the door and fanlight · about 1.14 mCombustion readings at maximum and minimum rateAshcroft CX30 combi, kitchen external wall
The flue terminal and the back door (a slow pan over a still)
Try the boiler commissioning form live
Answer a few questions and watch it adapt. Your answers are not saved, and any photos you add are deleted within the hour.
Live form: Boiler Installation and Commissioning RecordOpen full screen ↗
Fill it in right here
This is the real form as your team would use it: questions appear as you answer, scores work themselves out and you can add photos and signatures. No sign-up needed. Or open a completed example to see every answer, photo and score filled in.
Every question in the boiler commissioning template
A gas boiler installation and commissioning record: boiler and flue, gas pressure and rate, tightness, combustion at maximum and minimum rate, system cleaning and inhibitor, controls, CO alarm, Gas Safe notification and Benchmark. 4 sections and 56 questions. Follow-up questions and guidance appear only when an answer calls for them, so the person on site never sees the ones that do not apply.
✎
Make it your own: every question is editable
This is a starting point, not a fixed form. Once it is in your SiteSurvey account you can reword any question, add or remove questions, sections and answer options, and add your own logo, so it fits the way your team works and the jobs you do.
Details you only enter once
Add this form to a project in SiteSurvey and it fills in what the project already knows, so nobody on site retypes it and every form on the job uses the same names. Anything filled in can still be changed.
Project: the project name
Client: the project's customer
Site: the site, when the form is opened for a space or a product
Site address: the site address, from the space or the project
1
Boiler
ProjectShort answer
Fills in from the project name
ClientShort answer
Fills in from the project's customer
Site*Short answer
Fills in from the site, when the form is opened for a space or a product
Site addressShort answer
Fills in from the site address, from the space or the project
Date commissioned*Date
Time commissionedTime
Engineer name*Short answer
Gas Safe registration number (business)*Short answer
Engineer licence numberShort answer
Boiler make and model*Short answer
Scan the data plateScan a label: serial number, gc number
Optional. Scan the label or tag to capture its numbers.
TypeChoose one
Combi
System
Regular (heat only)
LocationShort answer
CheckGas work must be done by a Gas Safe registered engineer under the Gas Safety (Installation and Use) Regulations 1998; regulation 26 requires the installer to check the flue, the combustion air supply, the operating pressure or heat input and the safe operation of the appliance before leaving it. Domestic boilers are installed to BS 6798 and the manufacturer instructions, and combustion is measured with an analyser used to BS 7967.
CheckThis is a site record of the commissioning. It supports the Benchmark commissioning checklist and the building regulations notification made through Gas Safe Register; it is not the Benchmark checklist, the Building Regulations compliance certificate or a gas safety record.
2
Gas, flue and combustion
Flue typeChoose one
Horizontal balanced
Vertical balanced
Plume management kit
Other
Flue terminal position meets the manufacturer's clearances?Yes or No
Smallest distance from the flue terminal to an opening window, door or air brick (m)Number
Measure from a photo taken square on to the wall, using a door or window of known size as the reference. It is an estimate; anywhere near the minimum, check with a tape.
Shown when “Flue type” is answered
Minimum for that opening in the manufacturer's instructions (m)Number
Shown when “Flue type” is answered
Terminal distance against the instructionsWorked out by the form
Shown when “Smallest distance from the flue terminal to an opening window, door or air brick (m)” is answered and “Minimum for that opening in the manufacturer's instructions (m)” is answered
Gas tightness test*Choose one
Pass
Fail
Working inlet pressure (mbar)Number
Minimum working inlet pressure in the manufacturer's instructions (mbar)Number
Inlet pressure against the instructionsWorked out by the form
Shown when “Working inlet pressure (mbar)” is answered and “Minimum working inlet pressure in the manufacturer's instructions (mbar)” is answered
Gas rate measured (m³/h or kW)Number
CO at maximum rate (ppm)Number
CO/CO2 ratio at maximum rateNumber
CO at minimum rate (ppm)Number
CO/CO2 ratio at minimum rateNumber
Highest CO allowed in the manufacturer's instructions (ppm)Number
Highest CO/CO2 ratio allowed in the manufacturer's instructionsNumber
At maximum rateWorked out by the form
Shown when “CO at maximum rate (ppm)” is answered and “CO/CO2 ratio at maximum rate” is answered and “Highest CO allowed in the manufacturer's instructions (ppm)” is answered and “Highest CO/CO2 ratio allowed in the manufacturer's instructions” is answered
At minimum rateWorked out by the form
Shown when “CO at minimum rate (ppm)” is answered and “CO/CO2 ratio at minimum rate” is answered and “Highest CO allowed in the manufacturer's instructions (ppm)” is answered and “Highest CO/CO2 ratio allowed in the manufacturer's instructions” is answered
WarningA combustion reading is over the manufacturer's limit. Investigate as the manufacturer's instructions say before the boiler is handed over, and follow the gas industry unsafe situations procedure where it applies.
Shown only when the answers above make it relevant
GuidanceCombustion readings are compared with the limits in the manufacturer's instructions, and recorded on the Benchmark commissioning checklist.
Condensate pipe run and terminated correctly?Yes or No
Results needing attentionWorked out by the form
Counts a failed tightness test, inlet pressure below the minimum, combustion over a limit at either rate, a terminal too close to an opening or outside the clearances, and condensate not run correctly.
CheckA result needs attention. Record what was put right before handover in the photos and notes, or why the boiler was not left in use.
Shown only when the answers above make it relevant
3
System and controls
System cleaned and flushed?Yes or No
Inhibitor added?Yes or No
System filter fitted?Yes or No
Controls fittedTick all that apply
Programmer or timer
Room thermostat
Thermostatic radiator valves
Weather compensation
Smart thermostat
Other (describe)
Hot water outlet temperature (°C)Number
Carbon monoxide alarm fitted in the room with the boiler?Yes or No
WarningApproved Document J (England), paragraph 3.43: where a new or replacement fixed gas appliance, other than one used only for cooking, is installed in a home, a carbon monoxide alarm should be provided in the room where it is located.
Shown when “Carbon monoxide alarm fitted in the room with the boiler?” is No
4
Notification and handover
Gas Safe building regulations notification referenceShort answer
GuidanceBenchmark: every installation must be notified to building control, directly or through a competent person scheme such as Gas Safe Register, and a Building Regulations compliance certificate is then issued to the homeowner. GOV.UK says a scheme installer gives the certificate within 8 weeks of completion.
Benchmark commissioning checklist completed?Yes or No
Customer shown how to use the boiler and controls, and asked to sign the Benchmark checklist?Yes or No
Warranty registered with the manufacturer?Yes or No
CheckWarranty terms are set by each manufacturer and can include a deadline for registration. Check the manufacturer's terms.
Shown when “Warranty registered with the manufacturer?” is No
Photos of the boiler, flue and controlsPhotos
Defects and actions
Repeat for each action. Each one asks:
Action needed*Notes
PriorityChoose one
Urgent
High
Medium
Low
OwnerShort answer
Due dateDate
StatusChoose one
Open
In progress
Completed
PhotosPhotos
First service dueDate
Usually 12 months after commissioning. Check the manufacturer instructions and warranty terms.
Days to first serviceWorked out by the form
Shown when “Date commissioned” is answered and “First service due” is answered
CheckThe next due date is before the date of this record. Check the date entered.
Shown only when the answers above make it relevant
Customer nameShort answer
Customer signatureSignature
Installer nameWorked out by the form
Engineer signatureSignature
See it filled in
A completed boiler commissioning report, made by SiteSurvey from a fictional site visit: every answer, the photos, the guidance that applied and the sign-off, ready to send as a PDF.
The form records CO and the CO/CO2 ratio at maximum and minimum rate. Enter the limits from the manufacturer's instructions and it marks each rate within the limits or over a limit, with a red note to investigate before handover. Record the readings on the Benchmark commissioning checklist too.
Who notifies the installation?
Benchmark says every installation must be notified to building control, directly or through a competent person scheme such as Gas Safe Register, and a Building Regulations compliance certificate is then issued to the homeowner. The form records the notification reference.
Does a new boiler need a carbon monoxide alarm?
In England, Approved Document J (paragraph 3.43) says that where a new or replacement fixed gas appliance, other than one used only for cooking, is installed in a home, a carbon monoxide alarm should be provided in the room where it is located. The form asks and warns if there is none.
Does the warranty need registering?
Warranty terms are set by each manufacturer. Benchmark says installers must install, commission and service in line with the Benchmark checklist for warranty purposes. The form records whether the Benchmark checklist was completed and the warranty registered.
Is this the Benchmark checklist?
No. It is your own site record, with photos and signatures, that sits alongside the Benchmark checklist. The form asks whether Benchmark was completed and whether the customer was shown how to use the boiler and controls.
Who uses this?
Gas Safe registered heating engineers and installers, and housing providers replacing boilers.