Demolition plan template

For people assembling information for competent demolition planning. Record structure and information, sequence and controls and readiness. Try the form below, see every question or open a completed example.

Ready to use from the form library, and every question is yours to edit. Try it for a small trial fee, cancel any time.

Try it on your phone

Try it on this phone

Fill in the demolition planning record on your phone now

See how the demolition planning record looks on your phone

Scan the code with your phone camera. It opens the real form, no sign-up needed.

Open the live example and fill it in, just as your team would on site. No sign-up needed.

See it on this phone

Every question is editable. Add this form to your account, then change the wording, add or remove questions and options, and make it fit your own jobs.

Or start your trial with this form ready →

One email, and we won't add you to a mailing list.

How must demolition be planned?

HSE says demolition and dismantling must be planned and carried out by competent people to avoid unplanned collapse. Relevant structural information, work sequence and precautions need to be established before work begins.

Last updated . Facts checked by the SiteSurvey team on 6 October 2026 against HSE demolition and HSE structural stability during demolition.

Try the demolition planning record form live

Answer a few questions and watch it adapt. Your answers are not saved, and any photos you add are deleted within the hour.

Live form: Demolition Planning RecordOpen full screen ↗
Fill it in right here

This is the real form as your team would use it: questions appear as you answer, scores work themselves out and you can add photos and signatures. No sign-up needed. Or open a completed example to see every answer, photo and score filled in.

Want to see one filled in? See a completed demolition planning record report (PDF), made by SiteSurvey from a fictional site visit.

Fill it in on a phone or tablet

Your team completes the demolition planning record on site in the SiteSurvey app on iPhone, iPad and Android phones and tablets. The project name and address fill in for them, it works without signal, and it syncs when the device is back online with photos kept against the question they answer.

Customers and subcontractors do not need the app: send them a link and they can fill it in from any browser.

The Demolition Planning Record form in the SiteSurvey app on a tablet
The Demolition Planning Record form in the SiteSurvey app on a phone

Every question in the demolition planning record template

A demolition planning record linking surveys, structural advice, service isolation, sequence, exclusion zones, waste arrangements and hold-point reviews. 6 sections and 41 questions. Follow-up questions and guidance appear only when an answer calls for them, so the person on site never sees the ones that do not apply.

Make it your own: every question is editable

This is a starting point, not a fixed form. Once it is in your SiteSurvey account you can reword any question, add or remove questions, sections and answer options, and add your own logo, so it fits the way your team works and the jobs you do.

Details you only enter once

Add this form to a project in SiteSurvey and it fills in what the project already knows, so nobody on site retypes it and every form on the job uses the same names. Anything filled in can still be changed.

  • Project: the project name
  • Site or premises address: the site address, from the space or the project
  • Client or organisation: the project's customer

Record details and scope

  • ProjectShort answer

    Filled in from the project in SiteSurvey.

    Fills in from the project name
  • Site or premises addressShort answer
    Fills in from the site address, from the space or the project
  • Client or organisationShort answer
    Fills in from the project's customer
  • Record date*Date
  • Person completing the record*Short answer
  • CheckThis organises planning evidence. It is not a demolition design, structural survey, asbestos survey, method statement or authorisation to start demolition.
  • CheckSources. The Construction (Design and Management) Regulations 2015 (CDM 2015), regulation 20: demolition or dismantling must be planned and carried out to prevent danger or reduce it as low as reasonably practicable, and the arrangements must be recorded in writing before the work begins. BS 6187:2011 (Code of practice for full and partial demolition) covers planning, surveys, sequence and competence. The Control of Asbestos Regulations 2012, regulation 5: before demolition work, the presence, type and condition of asbestos must be identified, normally by a refurbishment and demolition survey. The Building Act 1984, sections 80 and 81, require notice to the local authority before most demolitions.

Structure and information

  • Structure and extent of proposed demolition*Short answer
  • Competent demolition designer or engineer*Short answer
  • Structural, asbestos and other survey references*Notes
  • Adjacent buildings, public interfaces and servicesNotes
  • Is a refurbishment and demolition asbestos survey held for everything to be demolished?Yes or No
  • Survey reference and dateShort answer
    Shown when “Is a refurbishment and demolition asbestos survey held for everything to be demolished?” is Yes
  • WarningNo demolition asbestos survey. The Control of Asbestos Regulations 2012, regulation 5, requires asbestos to be identified before demolition. Do not start demolition until a refurbishment and demolition survey has been done and any asbestos found has been dealt with.
    Shown when “Is a refurbishment and demolition asbestos survey held for everything to be demolished?” is No
  • Date the section 80 demolition notice was given to the local authorityDate

    Building Act 1984, section 80. Copies go to the occupiers of adjacent buildings and the gas and electricity suppliers. Some small and internal demolitions are exempt.

  • Section 81 counter-notice reference and dateShort answer

    Leave blank if the local authority has not yet replied.

  • CheckNot yet clear to start. Demolition must not start until the local authority has given a section 81 notice or 6 weeks have passed since the section 80 notice.
    Shown only when the answers above make it relevant
  • Photos of the structure before workPhotos
  • Photos of adjacent buildings before workPhotos

    Record the existing condition of neighbouring walls, roofs and boundaries.

  • Walk Cam: pre-demolition walk-roundWalk Cam video with voice-to-text

    Optional. Film a guided walk-through on the SiteSurvey app.

Sequence and controls

  • Demolition stage
    Repeat for each demolition stage. Each one asks:
    • Stage and drawing reference*Short answer
    • Engineered sequence and stability assumptions*Notes
    • Exclusion, support, plant and dust controls*Notes
    • Hold point and person authorising progression*Short answer

Readiness

  • Service disconnection and verification references*Short answer
  • Temporary works design and check referencesShort answer
  • Material segregation and hazardous waste arrangementsNotes
  • Emergency and unintended movement responseNotes

Review and changes

  • Information gaps and restrictions*Notes

    Identify missing survey or design information and the work affected. Record who must resolve it before the relevant stage can be reviewed.

  • Separate approved method and review referencesShort answer
  • Change-control and briefing arrangementsNotes

Actions and review

  • Are further actions required?*Choose one
    • Yes
    • No
  • Further action
    Repeat for each further action. Each one asks:
    Shown when “Are further actions required?” is “Yes”
    • Action and evidence reference*Notes
    • PriorityChoose one
      • Urgent
      • High
      • Medium
      • Low
    • Person responsible*Short answer
    • Target dateDate
    • Action status*Choose one
      • Open
      • In progress
      • Completed
    • Completion evidenceNotes
      Shown when “Action status” is “Completed”
  • Outstanding limitations and information to pass onNotes
  • Record status*Choose one
    • Ready for review
    • Further work needed
    • Work or use stopped
  • Reviewed byShort answer
  • Review dateDate
  • Author signature*Signature
  • Principal contractor approval: name and positionShort answer
  • Principal contractor signatureSignature
  • CheckSigning records the information entered. It does not itself certify legal compliance, remove a limitation or authorise unsafe work.

Scope and responsibility

This organises planning evidence. It is not a demolition design, structural survey, asbestos survey, method statement or authorisation to start demolition.

What a useful entry looks like

Information gaps and restrictions

Identify missing survey or design information and the work affected. Record who must resolve it before the relevant stage can be reviewed.

Information about the concealed connection is incomplete. The affected stage remains unresolved pending the designer's review and supporting survey evidence.

Fictional example of record wording. Use the actual evidence and approved arrangements for your job; this is not a completed report or an instruction to carry out the work.

See it filled in

A completed demolition planning record report, made by SiteSurvey from a fictional site visit: every answer, the photos, the guidance that applied and the sign-off, ready to send as a PDF.

See completed form (PDF) ↗

Demolition Planning Record FAQs

How should I record “Information gaps and restrictions”?

Identify missing survey or design information and the work affected. Record who must resolve it before the relevant stage can be reviewed.

Can a generic sequence be used for any building?

No. The competent team must determine the sequence for the actual structure and conditions.

Does this replace an asbestos survey?

No. Record the appropriate survey reference and how its findings affect the work.

What if unexpected construction is exposed?

Stop the affected work under the agreed procedure and obtain competent review before changing the sequence.

What are the limits of this template?

This organises planning evidence. It is not a demolition design, structural survey, asbestos survey, method statement or authorisation to start demolition.

Can I complete this form on site and share the record?

In the SiteSurvey app the form works offline, with signatures recorded against the questions. Share the completed record as a PDF or a link. Dates and action owners are recorded fields; this form does not send reminders or update other systems.

Related

Hazards this form covers

Who each hazard harms, what the law expects and the control measures to look for, in our hazard library.

Related templates

Construction phase plan template

A construction phase plan record covering the team, programme, site rules, welfare, significant risks, emergency arrangements and revisions.

6 sections · 37 questions · See every question →
Pre construction information template

A pre-construction information register with existing records, site constraints, significant risks, information gaps, recipients and issue revisions.

6 sections · 39 questions · See every question →
Design risk register template

A design risk register linking design decisions, foreseeable lifecycle hazards, elimination options, residual risks, drawings and dutyholder communication.

5 sections · 41 questions · See every question →
Pre-demolition survey

A pre-demolition survey and audit of a building: building details, survey scope and areas not accessed, the asbestos demolition survey and each material found or presumed (CAR 2012 and HSE in the UK, the NESHAP inspection in the US), lead, PCBs, fluorescent tubes, refrigerants, tanks, contaminated land and other hazards, services with disconnection dates, structural observations, a resource audit of materials for reuse and recycling by room or element with quantities and routes, neighbours, party wall and section 80 notices, recommendations, actions and sign-off.

10 sections · 158 questions · See every question →
Asbestos register and management plan template

An asbestos management record linking known or presumed materials to survey evidence, condition observations, controls, communication and review actions.

5 sections · 51 questions · See every question →

Browse all 428 forms in the library

Use this demolition planning record form with your team

Add it from the form library in one click, change any question, and every completed form becomes a branded PDF report.

Start your trial →