Skip to main content

Form library · Construction and handover

Practical completion certificate template

A practical completion certificate and handover record. Record the form of contract, the parties, the works, the date for completion and the date of practical completion; if it is late, the form shows the days late and, with the rate in the contract, the liquidated damages at that rate as arithmetic. Add any minor items still to finish with who will do them, dates, status and photos, and the form counts the open items and those with no owner or date. Record the rectification period and its end date, and the form checks they agree. Enter the contract sum, retention and the share released, and the form works out the retention held, released and still held. Then the handover documents and keys, and signatures from the contract administrator, contractor and client. Try the form below, see every question or open a completed example.

Ready to use from the form library, and every question is yours to edit. Try it for a small trial fee, cancel any time.

Try it on your phone

Try it on this phone

Fill in the practical completion certificate on your phone now

See how the practical completion certificate looks on your phone

Scan the code with your phone camera. It opens the real form, no sign-up needed.

Open the live example and fill it in, just as your team would on site. No sign-up needed.

See it on this phone

Every question is editable. Add this form to your account, then change the wording, add or remove questions and options, and make it fit your own jobs.

Or start your trial with this form ready →

One email, and we won't add you to a mailing list.

What does a certificate of practical completion do?

Under JCT contracts, and many others, the certificate records the date when the contract administrator considers the works complete for all practical purposes. It starts the rectification (defects) period, ends the contractor's liability for delay damages and is usually when part of the retention is released. The exact effect depends on the contract, so check its terms.

Last updated . Facts checked by the SiteSurvey team on 21 October 2026 against JCT: Minor Works Building Contract with contractor's design 2016, guidance notes, RICS Construction Journal: why professionals should be wary of practical completion, RICS practice information: defects and rectifications and regulation 12 of the Construction (Design and Management) Regulations 2015.

Built for practical completion and handover

Record the dates and the form shows the days late and, with the contract rate, liquidated damages at that rate as arithmetic. Add the minor items with owners, dates, status and photos, and the form counts the open ones. Enter the contract sum and retention, and it works out what is held, released and still held. The contract decides what is due.

Share of the retention released now 50%, with tiles £12,150 released now and £12,150 still held to the end of the rectification period

Retention worked out

Enter the contract sum, the retention percentage and the share released, and the form works out the retention held, released now and still held to the end of the rectification period.

How calculated fields work →
Tiles: 3 outstanding items, 2 still open, 0 with no owner, 0 with no date

Minor items counted

Each minor item has an owner, a date, a status and photos. The form counts the open items and those with no owner or no date, so the list can be closed.

How calculated fields work →
7 days after the date for completion, a liquidated damages rate of £1,500 per week and £1,500 at that rate

Days late

When practical completion is after the date for completion, the form shows the days late and multiplies the contract rate by the weeks as arithmetic only. Extensions and the contract decide what is due.

How calculated fields work →

Walk the finished rooms

Film the finished rooms with Walk Cam on the SiteSurvey app, so the minor items are clear to everyone at handover.

A completed practical completion certificate

A fictional surgery extension in Stroud: practical completion 7 days after the date for completion, three minor items with one finished, a 12-month rectification period, 5% retention on £486,000 with half released, and every handover document received.

A white painted door frame in a new corridor with chipped paint at hand height
Touch up the corridor door frames · open
A data outlet in a new waiting room wall with no faceplate and cables showing
Fit the data point cover plate · open

Try the practical completion certificate form live

Answer a few questions and watch it adapt. Your answers are not saved, and any photos you add are deleted within the hour.

Live form: Practical Completion CertificateOpen full screen ↗
Fill it in right here

This is the real form as your team would use it: questions appear as you answer, scores work themselves out and you can add photos and signatures. No sign-up needed. Or open a completed example to see every answer, photo and score filled in.

Want to see one filled in? See a completed practical completion certificate report (PDF), made by SiteSurvey from a fictional site visit.

Every question in the practical completion certificate template

A practical completion certificate: the contract, works and date of practical completion, outstanding minor items, the rectification period, retention, handover documents and signatures. 4 sections and 50 questions. Follow-up questions and guidance appear only when an answer calls for them, so the person on site never sees the ones that do not apply.

Make it your own: every question is editable

This is a starting point, not a fixed form. Once it is in your SiteSurvey account you can reword any question, add or remove questions, sections and answer options, and add your own logo, so it fits the way your team works and the jobs you do.

Details you only enter once

Add this form to a project in SiteSurvey and it fills in what the project already knows, so nobody on site retypes it and every form on the job uses the same names. Anything filled in can still be changed.

  • Project: the project name
  • Client: the project's customer
  • Site: the site, when the form is opened for a space or a product
  • Site address: the site address, from the space or the project

Contract

  • ProjectShort answer
    Fills in from the project name
  • ClientShort answer
    Fills in from the project's customer
  • Site*Short answer
    Fills in from the site, when the form is opened for a space or a product
  • Site addressShort answer
    Fills in from the site address, from the space or the project
  • Date of practical completion*Date
  • TimeTime
  • Form of contractChoose one
    • JCT Minor Works
    • JCT Intermediate
    • JCT Design and Build
    • JCT Standard Building
    • NEC
    • Other or none
  • Contract referenceShort answer
  • Employer or client*Short answer
  • Contractor*Short answer
  • Contract administrator or employer's agentShort answer
  • Description of the works*Notes
  • Date for completion in the contract, as extendedDate
  • CheckPractical completion is after the date for completion. Liquidated damages may be due under the contract for the delay.
    Shown only when the answers above make it relevant
  • Days after the date for completionWorked out by the form
    Shown only when the answers above make it relevant
  • Liquidated damages rate in the contract (£ per week)Number

    Optional. The form multiplies it by the weeks late as arithmetic only; the contract and any extensions decide what is due.

    Shown only when the answers above make it relevant
  • Liquidated damages at that rate (£)Worked out by the form
    Shown only when the answers above make it relevant
  • GuidanceUnder JCT contracts, and many others, practical completion starts the rectification (defects) period, ends the contractor's liability for delay damages and is when part of the retention is usually released. Check the terms of your contract.
  • CheckNEC contracts do not use practical completion. Under the NEC Engineering and Construction Contract the Project Manager certifies Completion, as defined in the contract, and the defects date and delay damages run from that. Record the Project Manager as the contract administrator below.
    Shown when “Form of contract” is “NEC”
  • CheckThis is a site record of the handover. Where the contract has its own certificate, such as the JCT Practical Completion Certificate or Statement, that certificate must still be issued by the person named in the contract. This record supports it and does not replace it.

Outstanding items

  • Are there minor items still to finish?Yes or No
  • Outstanding items
    Repeat for each item. Each one asks:
    Shown when “Are there minor items still to finish?” is Yes
    • Item*Short answer
    • LocationShort answer
    • Who will finish it?Short answer
    • To be finished byDate
    • StatusChoose one
      • Open
      • Finished
    • Days allowed after practical completionWorked out by the form
      Shown when “To be finished by” is answered and “Date of practical completion” is answered
    • PhotosPhotos
    • item_f_openWorked out by the form
    • item_f_noownerWorked out by the form
    • item_f_nodateWorked out by the form
  • Outstanding itemsWorked out by the form
    Shown when “Are there minor items still to finish?” is Yes
  • Still openWorked out by the form
    Shown when “Are there minor items still to finish?” is Yes
  • With no ownerWorked out by the form
    Shown when “Are there minor items still to finish?” is Yes
  • With no dateWorked out by the form
    Shown when “Are there minor items still to finish?” is Yes
  • CheckSome items have no owner or no date. Agree who will finish each one and by when, so the list can be closed.
    Shown only when the answers above make it relevant
  • Rectification period (months)Number
  • Rectification period endsDate
  • Months from practical completion to that dateWorked out by the form
    Shown when “Rectification period ends” is answered and “Date of practical completion” is answered
  • CheckThe end date does not match the rectification period in months. Check both against the contract.
    Shown only when the answers above make it relevant
  • WarningThe rectification period end date is before the date of practical completion.
    Shown only when the answers above make it relevant
  • Retention (%)Number
  • Contract sum or value of the works (£)Number

    Optional. Use the figure the retention is calculated on under your contract.

  • Retention held before practical completion (£)Worked out by the form
    Shown only when the answers above make it relevant
  • Retention released at practical completionShort answer
  • Share of the retention released now (%)Number

    For example 50 if half is released at practical completion. Check your contract.

    Shown only when the answers above make it relevant
  • Released now (£)Worked out by the form
    Shown only when the answers above make it relevant
  • Still held to the end of the rectification period (£)Worked out by the form
    Shown only when the answers above make it relevant

Handover documents

  • Handed overTick all that apply
    • Health and safety file
    • Operation and maintenance manuals
    • As-built drawings
    • Test and commissioning certificates
    • Building control completion certificate
    • Warranties and guarantees
    • Keys and access fobs
  • Handover documents received (of 7)Worked out by the form
  • CheckCDM 2015: where a project has more than one contractor, the principal designer prepares the health and safety file and passes it to the client at the end of the project, and the client keeps it available for anyone who needs it.
    Shown only when the answers above make it relevant
  • Number of keys or fobsNumber

Certificate

  • GuidanceThe contract administrator certifies that practical completion of the works was achieved on the date above.
  • Contract administrator name (the Project Manager under NEC)*Short answer
  • Contract administrator signatureSignature
  • For the contractorShort answer
  • Contractor signatureSignature
  • For the clientShort answer
  • Client signatureSignature

See it filled in

A completed practical completion certificate report, made by SiteSurvey from a fictional site visit: every answer, the photos, the guidance that applied and the sign-off, ready to send as a PDF.

See completed form (PDF) ↗

Practical completion certificate FAQs

Who issues the certificate?

Under JCT contracts, the architect or contract administrator certifies the date of practical completion. The form records who certifies it and has signatures for the contractor and client too.

Can there be outstanding items?

RICS notes that it is usual practice to issue a list of minor items at practical completion. Record each one with its location, who will finish it, a date and photos, so they are clear to everyone.

What is the rectification period?

The period after practical completion during which the contractor must put right defects that appear. Its length is set in the contract: JCT's Minor Works guidance gives 3 months unless otherwise agreed, and RICS notes that 12 or 24 months is often agreed. The form records the length and the end date.

What happens to the retention?

JCT's Minor Works guidance says 5 per cent is normally retained up to practical completion and the contract envisages that this is halved until the final certificate. RICS notes that the second half is returned once defects have been made good. The form records the percentage and the share released, and works out the amounts from the contract sum.

What if completion is late?

If the work is not finished by the date for completion, as extended, the employer can recover liquidated damages at the rate set in the contract. The form records the date for completion and warns when practical completion is later.

What documents are handed over?

Typically the health and safety file, operation and maintenance manuals, as-built drawings, test and commissioning certificates, the building control completion certificate, warranties and keys. On projects with more than one contractor, CDM 2015 has the principal designer pass the health and safety file to the client at the end. The form warns if it is missing.

Related

Use this practical completion certificate form with your team

Add it from the form library in one click, change any question, and every completed form becomes a branded PDF report.

Start your trial →