A non-conformance and corrective action report in five steps: what was found, containment, root cause using 5 whys, corrective actions, then verify and close. It suits a failed inspection on site, a customer complaint, a supplier problem or an audit finding. Mark where it was found with GPS, measure the defect from a photo, and the form counts open actions and the days the report has been open. Try the form below, see every question or open a completed example.
✎Every question is editable. Add this form to your account, then change the wording, add or remove questions and options, and make it fit your own jobs.
A non-conformance report should state the requirement and what actually happened, with evidence. It should record what was done straight away to contain the problem and what happens to the affected product or work. It then needs the root cause, corrective actions with an owner and a due date, and a later check that the actions worked before the report is closed.
Mark where the problem was found, measure the defect from a photo, then contain it, find the root cause with 5 whys and set corrective actions. The form counts open actions and the days the report has been open, and warns if it is closed with actions still open.
Defect size from a photo
Tape an A4 sheet beside the defect, photograph it square on and tap across both. The width and height go into the report with the marked-up photos, and the form works out the area. It works on web forms in any phone browser today, and the app version is on its way.
Add a short video of the defect and its surroundings to the evidence.
A completed non-conformance report
A fictional concrete frame: honeycombing about 0.32 by 0.26 m at the base of a column, measured from a photo with an A4 sheet, repaired to the engineer's instruction, with the pour method and pre-pour checklist changed and the report closed after 18 days.
Column B-C4 · honeycombing at the baseBlock B ground floor · other columns checked
Try the non-conformance report form live
Answer a few questions and watch it adapt. Your answers are not saved, and any photos you add are deleted within the hour.
Live form: Non-Conformance and Corrective Action ReportOpen full screen ↗
Fill it in right here
This is the real form as your team would use it: questions appear as you answer, scores work themselves out and you can add photos and signatures. No sign-up needed. Or open a completed example to see every answer, photo and score filled in.
Your team completes the non-conformance and corrective action report on site in the SiteSurvey app on iPhone, iPad and Android phones and tablets. The project name and address fill in for them, it works without signal, and it syncs when the device is back online with photos kept against the question they answer.
Customers and subcontractors do not need the app: send them a link and they can fill it in from any browser.
Every question in the non-conformance report template
Record a non-conformance, contain it, find the root cause with 5 whys, set corrective actions with owners and dates, then verify and close. 5 sections and 52 questions. Follow-up questions and guidance appear only when an answer calls for them, so the person on site never sees the ones that do not apply.
✎
Make it your own: every question is editable
This is a starting point, not a fixed form. Once it is in your SiteSurvey account you can reword any question, add or remove questions, sections and answer options, and add your own logo, so it fits the way your team works and the jobs you do.
Details you only enter once
Add this form to a project in SiteSurvey and it fills in what the project already knows, so nobody on site retypes it and every form on the job uses the same names. Anything filled in can still be changed.
Project: the project name
Customer: the project's customer
Site or department: the site, when the form is opened for a space or a product
Site address: the site address, from the space or the project
1
What was found
Raise it while the evidence is in front of you.
ProjectShort answer
Filled in from the project in SiteSurvey.
Fills in from the project name
Report numberShort answer
CustomerShort answer
Fills in from the project's customer
Site or department*Short answer
Fills in from the site, when the form is opened for a space or a product
Site addressShort answer
Fills in from the site address, from the space or the project
Where it was found (GPS)Short answer
Optional. Mark the position on site, such as a column, a chamber or a delivery bay.
Date raised*Date
Raised byShort answer
How was it found?Choose one
Internal audit
Inspection or test
Customer complaint
Supplier delivery
Observation on site or on the line
Incident or near miss
What is it about?Choose one
Product or material
Workmanship
A process not followed
A document or record
A supplier
Severity*Choose one
Minor
Major
Critical
GuidanceSource. ISO 9001:2015 clause 10.2 (nonconformity and corrective action): react to the nonconformity, correct it, find the cause, take action so it does not happen again, check the action worked, and keep documented information on each step.
What should have happened?Notes
The requirement: drawing, specification, procedure or standard, with its reference.
What did happen?*Notes
Facts only: what, where, when and how many.
Quantity or extent affectedShort answer
Width of the defect or affected area (m)Number
Optional. Measure from a photo with an A4 sheet, a door or a person in the same plane, or use a tape.
Height or length of the defect or affected area (m)Number
Area affected (m²)Worked out by the form
Shown only when the answers above make it relevant
Photos of the evidencePhotos
2
Containment
Stop it spreading before you work out why.
What was done straight away?Notes
What happens to the affected product or work?Choose one
Quarantined
Reworked or repaired
Scrapped
Returned to the supplier
Used as it is, with approval
Not applicable
Who approved using it as it is?Short answer
Shown when “What happens to the affected product or work?” is “Used as it is, with approval”
Could other batches, sites or jobs have the same problem?Yes or No
What has been checked?Short answer
Shown when “Could other batches, sites or jobs have the same problem?” is Yes
Does the customer need to be told?Yes or No
Who was told, and when?Short answer
Shown when “Does the customer need to be told?” is Yes
3
Root cause: 5 whys
Ask why until you reach something you can change.
GuidanceStart from what happened and ask why. Take each answer and ask why again. Five is a guide, not a rule: stop when the answer is a process, a method or a missing control that you can change, not a person to blame.
Why did it happen?Short answer
Why was that?Short answer
Shown when “Why did it happen?” is answered
Why was that?Short answer
Shown when “Why was that?” is answered
Why was that?Short answer
Shown when “Why was that?” is answered
Why was that?Short answer
Shown when “Why was that?” is answered
Root cause*Notes
Where does the cause sit?Choose one
People and training
Method or procedure
Material
Machine or equipment
Measurement
Environment
Other (describe)
Should an existing check have caught this earlier?Yes or No
Why did it not?Short answer
Shown when “Should an existing check have caught this earlier?” is Yes
4
Corrective actions
Fix this one, then stop it happening again.
Actions
Repeat for each action. Each one asks:
Action*Notes
PriorityChoose one
Urgent
High
Medium
Low
TypeChoose one
Correction: fixes this case
Corrective action: removes the cause
OwnerShort answer
DueDate
CompletedDate
ActionsWorked out by the form
CompletedWorked out by the form
Still openWorked out by the form
5
Verify and close
Check the fix worked before you close the report.
Date effectiveness was checkedDate
Did the actions work?Choose one
Yes
No
Too early to say
What evidence did you look at?Notes
Which procedures, risks or documents have been changed?Notes
CheckThe cause has not been removed. Go back to the 5 whys: the root cause was probably one step further on.
Shown when “Did the actions work?” is “No”
Status*Choose one
Open
Closed
Date closedDate
Shown when “Status” is “Closed”
Days openWorked out by the form
Shown when “Date raised” is answered
CheckActions are still open. Close the report only when every action is complete and the check shows they worked.
Shown only when the answers above make it relevant
Closed byShort answer
Shown when “Status” is “Closed”
SignatureSignature
Shown when “Status” is “Closed”
See it filled in
A completed non-conformance report report, made by SiteSurvey from a fictional site visit: every answer, the photos, the guidance that applied and the sign-off, ready to send as a PDF.
Yes. It counts the days from the date raised to the date closed, or to today while the report is open, and shows how many actions are still open. A note appears if the report is closed with actions still open.
How does the 5 whys root cause analysis work in the form?
Start from what happened and ask why. Each answer opens the next why, up to five. Five is a guide, not a rule, and you may reach the cause in fewer: stop when the answer is a process, a method or a missing control that you can change, not a person to blame. You then record the root cause and where it sits, such as method, material, equipment or training.
What is the difference between a correction and a corrective action?
The form uses correction for an action that fixes this case, such as reworking the part, and corrective action for one that removes the cause so it does not happen again. Each action has an owner, a due date and a completed date, and the form counts the actions and how many are done.
Can I use it as an 8D or CAPA report?
It covers the same ground in fewer steps: describe the problem, contain it, find the root cause, set corrective actions, verify they worked and close. It does not use the 8D numbering or team roles. The form can be edited in SiteSurvey if your customer needs their own headings.
What does containment record?
What was done straight away, and what happens to the affected product or work: quarantined, reworked, scrapped, returned to the supplier or used as it is with approval, naming who approved it. It also asks whether other batches, sites or jobs could have the same problem and whether the customer needs to be told.
How is a report closed?
By checking the actions worked. The form records the date effectiveness was checked, the evidence looked at, which procedures or documents were changed and whether the actions worked. If they did not, it sends you back to the 5 whys. The person closing the report signs on the device. In the SiteSurvey app it works offline and syncs when the device is back online, and the record goes out as a PDF or a share link.
Can it be used after an incident or near miss?
Yes: choose incident or near miss as how it was found. HSE's investigation workbook follows the same path: gather the information, analyse it, decide the risk controls and act on an action plan. Record the incident itself on an incident report as well.